IEE study of Upper Kabeli Hydropower Project
Introduction
Narrative description of the Project:
construction and operation of 9.6MW Upper Kabeli Hydropower Project
Description of Actual Service Provided: Preparation of Terms of Reference and Report on Initial Environmental Examination (IEE) study, which includes: (a) Preparation and approval of IEE of Upper Kabeli Hydropower Project, (b) baseline data collection of biophysical, socio-economic as well as cultural environment, (c) public consultation, (d) Preparation of draft and final IEE report of entire projects, (e) incorporation of comments from DoED
Project Duration
Start Date: 2018-02-01
End Date: 2020-05-30
Location: Panchthar, Taplejung
Client: Arun Valley Hydropower Development Company Limited
Status: completed