IEE study of Grid Connected Solar Energy Project in Chandranigahpur, Rautahat, Duhabi, Sunsari, Dhalkebar, Dhanusha, Butwal, Rupandehi, Simara
Introduction
Narrative description of the Project:
construction and operation of Solar Energy Project in Chandranigahpur, Rautahat (4MW), Duhabi, Sunsari (1.5MW), Dhalkebar, Dhanusha (1MW), Butwal (8.5MW), Rupandehi (8.5MW), Simara (1MW) in various parts of Terai region of Nepal
Description of Actual Service Provided: Preparation of Terms of Reference and IEE Report on Initial Environmental Examination (IEE) study, which includes: (a) Preparation and approval of IEE of various solar Projects as mentioned above, (b) baseline data collection of biophysical, socio-economic as well as cultural environment, (c) public consultation, (d) Preparation of draft and final IEE report of entire projects, (e) incorporation of comments from DoED
Project Duration
Start Date: 2018-03-01
End Date: 2020-03-30
Location: Rautahat, Sunsari, Dhanusa, Rupandehi, Bara
Client: South Asian Engineering Pvt. Ltd.
Status: completed