IEE study of Daraundi-New Marsyangdi Joint 132kV Transmission Line Project – ESN

Completed

IEE study of Daraundi-New Marsyangdi Joint 132kV Transmission Line Project

Introduction

The Daraundi-New Marsyangdi 132kV Joint Transmission Line Project shall establish a common optimal line to evacuate power from the HPPs being developed/planned by various IPPs to the New Marsyangdi substation of National Grid hence reducing the technical losses, improving line voltage and protecting the environment by reducing the RoW and conserving the forest area.

Project Duration

Start Date: 2020-07-03
Location: Gorkha, Tanahu
Client: Rastriya Prasaran Grid Company Limited (RPGCL)
Status: ongoing