IEE study of 132kV Transmission Line of Khimti-2 Hydropower Project, Ramechhap
Introduction
Construction of 1.8km 132kV Transmission Line of Khimti-2 Hydropower Project (48MW), Ramechhap
Project Duration
Start Date: 2022-07-08
Location: Ramechhap
Client: Peoples Energy Limited