IEE study for 132kV Transmission Line of Kabeli B1 Hydropower Project
Introduction
Narrative description of the Project:
construction and operation of 132kV transmission line of Kabeli B1 Hydropower Project
Description of Actual Service Provided: Preparation of Report on Initial Environmental Examination (IEE) study, which includes: (a) Preparation and approval of IEE of 132kV Transmission Line of Kabeli B1 Hydropower Project, (b) baseline data collection of biophysical, socio-economic as well as cultural environment, (c) public consultation, (d) Preparation of draft and final IEE report of entire projects, (e) incorporation of comments from Department of Electricity Department (DoED)
Project Duration
Start Date: 2016-09-01
End Date: 2016-12-30
Location: Panchthar
Client: Arun Kabeli Power Limited
Status: completed