EIA study of Raksaul-Amlekhgunj Petroleum Pipeline Project

Introduction

Narrative description of the Project:

construction and operation of 36.02km petroleum pipeline

Description of Actual Service Provided: Preparation of Scoping Document, Terms of Reference and report for Environmental Impact Assessment (EIA) study, which includes: (a) Preparation and approval of EIA of Petroleum pipeline project, (b) baseline data collection of biophysical, socio-economic as well as cultural environment, (c) public consultation and Public Hearing, (d) Preparation of draft and final EIA report of entire project, (e) incorporation of comments from MoFE

Project Duration

Start Date: 2017-06-01
End Date: 2018-10-30
Location: Parsa and Bara
Client: Nepal Oil Corporation and Plan8 Nepal Pvt. Ltd.
Status: completed